Hi Gordon
Its 8.82 (8.82.071) PL08
It was backflush but now on manual/issue.
When I trace the journal entries I see the following is currently occurring in SAP and was wondering if this is correct:
1. Raise production order and released:
DR WIP $0
CR SOH $0
2. Production order is receipted/ (same as closed?):
DR WIP $0
CR COS $0
3. DR (BS) WIP 3,406
CR (BS) SOH $3,406
DR (BS) SOH $3,406
CR (BS) WIP $3,406
If any variance will go to WIP variance account on the P & L.
It appears WIP is in and out in the same transaction so currently on the BS you can't trace how much WIP is at a point in time as it goes in and out in the one transaction - is that correct?
Thanks ]